Objective:
Inconsistent equipment performance (output) is leading to the plant not being able to meet its external demands on the Companion line. Our affiliates have increased our output requirements on the Companion product line by 160,000 units from 07 Oct 13. An additional 1,500 units per shift, based on a 5 day 2 shift cycle between 07 Oct 13 and 20 Dec 13.
Inconsistent equipment performance (output) is leading to the plant not being able to meet its external demands on the Companion line. Our affiliates have increased our output requirements on the Companion product line by 160,000 units from 07 Oct 13. An additional 1,500 units per shift, based on a 5 day 2 shift cycle between 07 Oct 13 and 20 Dec 13.
Metric
|
Baseline
|
Goal
|
Blue Sky
|
Line OEE
improvement
|
59%
|
70%
|
75%
|
Unit
Output Equivalent
|
8,496
|
10,080
|
10,800
|
In order to avoid the costly option of Over Time to meet with this demand, the decision was taken to take a look at the line performance from start to finish, this involves the buy-in and commitment of all stakeholders involved - Suppliers, Planning, Manufacturing, Engineering and QA.
Proposed Project Timelines of DMAIC Phases:
2013 | ||||||||||||
October | November | December | ||||||||||
W41 | W42 | W43 | W44 |
W45 | W46 | W47 | W48 | W49 | W50 | W51 | W52 | |
Define | ||||||||||||
Measure | ||||||||||||
Analyse | ||||||||||||
Improve | ||||||||||||
Control |